試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project initiation phase, the project manager becomes aware that the stakeholders may be influencing the project in multiple positive and negative ways. What should the project manager do in this situation?
A、Assign a task to top management and the project sponsor to reduce the number of stakeholders
B、Perform a stakeholder analysis and group the stakeholders by using a power/interest grid
C、Concentrate management actions on key stakeholders
D、Update the risk register